ILC - International Linear Collider
 

Conventional Facilities and Siting

Click HERE for CFS Post Vancouver Materials
Files are Draft and arranged by dates

CRITERIA SHEET (Vancouver Version)
Complete Spreadsheet Jul 11 2006
BDS Jul 11 2006
DAMPING RING Info Jun 21 2006)
MAIN LINAC Jun 23 2006
e+ Source Undulator Electrical Jun 5 2006
RTML info May 25 2006
ELECTRON SOURCE Apr 18 2006
POSITRON SOURCE Apr 27 2006
RTML Optics Parts List Apr 13 2006
Preliminary Cryogenic Civil requirement Mar 31 2006

BULLET POINTS (Basis of Vancouver Estimate)
AIR TREATMENT 9-25-06
MAIN LINAC 9-21-06
DAMPING RING 9-21-06
BDS 9-21-06
RTML 9-20-06
SOURCES 9-20-06
WATER 9-20-06
POWER Americas 9-19-06
POWER Europe 9-19-06
SURVEY 9-15-06
HANDLING 9-15-06\\
LAYOUT (All layout are draft for comments)
U-1 Underground Structures Key Plan - Jul 12 2006
U-2 Underground Structures Elevation View - Jul 12 2006
U-3 e- Damping Ring Plan - Jul 12 2006
U-4 e- RTML Plan View - Jul 12 2006
U-5 Undulator Area & Main Linac Plan - Jul 12 2006
U-6 BDS Plan View - Jul 12 2006
U-7 BDS Details - Jul 12 2006
U-8 BDS Section View- Jul 12 2006
U-9 KAS & Main Linac Plan View - Jul 12 2006
U-10 e+ Damping Ring Plan View - Jul 12 2006
U-11 e+ RTML Plan View - Jul 12 2006
U-12 5m Service Tunnel Plan & Elevation View - Jul 12 2006
U-13 Access Passage - Plan & Section Jul 12 2006
M-1 Water Plant Thermal Capacity Jul 12 2006
M-2 Ventilation Schematic Jul 12 2006
ILC Overall Schematic Layout Jul 12 2006
Shaft 9 e- Injection Hall & RTML cavern Jul 12 2006
e-source RTML & DR Jul 12 2006
Zoom View of e- RTML & DR on e- end Jul 12 2006
Water Plant with WBS Jul 10 2006
e+ Source Target Area Undulator Jul 4 2006
BDS Exp Hall ALTERNATIVE "B" Jul 4 2006
Shaft 8 Cavern RTML & e+source Jul 3 2006
Cavern in ML & RTML for 14m Shaft Jun 30 2006
BDS Exp Hall ALTERNATTIVE "A" Jun 30 2006
BDS Beam Dump Layout Jun 29 2006
RTML Beam Dump Layout Jun 29 2006
ILC Alcove DR Shaft 9m Jun 21 2006
RTML Connecting Cavern Jun 15 2006
Space Temperature Jun 13 2006
ILC Ventilation Jun 9 2006
RDR BDS Layout Jun 8 2006
RDR Schematic Layout Jun 8 2006
Surface Central Plant Jun 6 2006
Experimental Hall Jun 6 2006
e- Source 5 GeV Injector Jun 2 2006
e+ e- Aux Gun & KAS Jun 2 2006
e+ Undulator Jun 2 2006
Water Plant at Shaft 7 Jun 1 2006
ILC 9m Shaft Cross Section w 1 Ton Lift May 24 2006
ILC 9m Shaft Cross Section w 1 Ton Lift May 24 2006
ILC 9m Shaft Cross Section w 3 Ton Lift May 18 2006
ILC 14m Shaft Cross Section w 3 Ton Lift May 18 2006
For reference-Cryomodule Layout May 4 2006
Process Cooling Water Distribution May 2 2006
e-Source Apr 28 2006
e+ xfr to-from booster to pdr Apr 27 2006
e+Kas Booster Source Apr 26 2006
Schedule scenarios Apr 26 2006
Air Treatment-Ventilation Apr 18 2006
e+Undulator Source Apr 17 2006
Shaft & Cavern Section Apr 7 2006
Power Distribution
Tunnel Drainage\\

MISC
Surface Building Included Items Jun 23 2006
Surface Buildings Jun 16 2006
Surface Buildings May 26 2006
Egress Comparison Sheet Apr 7 2006
Sharing Of Effort Regionally Mar 09 2006\\

WBS (Draft)
WBS Definitions Jun 09 2006
WBS Structure Jun 09 2006\\
ENGINEERING CHANGE PROPOSAL (ECP)
Blank Form (xls)

 
cfs/cfs_home.txt · Last modified: 2006/10/03 14:20 by cfs
 
Recent changes RSS feed